Saturday, October 22, 2011

LURC Voices Decision to Preserve the Downeast Lakes Watershed

Three days ago, approximately 50 people gathered at the Waterfront Event Center in Lincoln to hear LURC Commissioners give their final deliberations on First Wind’s permit application for the Bowers Wind Project.  This has been a long process, with First Wind (Champlain Wind LLC) submitting their application on January 21, 2011.  On March 14th, it was accepted by LURC staff as complete for processing, and the “expedited wind clock” began ticking.

Under the Maine Wind Energy Act, which designated 2/3 of the state of Maine as an “Expedited Wind Permitting Area”, regulatory agencies such as LURC and the DEP must fast-track wind development permits.  Once an application is deemed ‘complete’, a decision is required within 180 days if no public hearing is granted and within 270 days if the citizens of Maine are allowed the opportunity to participate in the process.

Tick-tock-tick-tock…
The Partnership for the Preservation of the Downeast Lakes Watershed (www.ppdlw.org) a nonprofit organization committed to protecting the beautiful Downeast Lakes region, applied for “intervenor status”, as did the Natural Resources Council of Maine (NRCM) and the Conservation Law Foundation (CLF).  Citizens David Corrigan and Gordon Mott also intervened.  First Wind’s plans for Bowers had been in the works for months, and finally, the wait was over.  The clock was ticking. 

Suddenly there were deadlines to be met and procedures to follow.  But before the intervenors could file any comments or submit pre-filed testimony, the long and complex permit application had to be examined.  First Wind’s consultants and attorneys had had months to prepare the application; but intervenors had only weeks to study hundreds of pages of text and graphs, maps and photos.  Only days to request a public hearing.

Tick-tock-tick-tock...

PPDLW is an all-volunteer organization, supported by locals and by non-residents who recreate in the Downeast lakes region.  The people of the Bowers Mountain area were fortunate to have several dedicated, hard-working and tenacious people prepared to mount a stiff opposition to First Wind’s 27 turbine project which—if permitted--would tower over Junior, Scraggly, Pleasant, Duck, Keg, Bottle and Shaw Lakes, among others.  Pre-filed testimony was filed.  A pre-hearing conference was attended.  The dates for Public Hearings were set.  June 27th.  June 28th.  July 6th.

Tick-tock-tick-tock…

I was able to travel to Lincoln to attend the technical and public hearings, and to go on the site visit, which included bus trips to the targeted ridges and a boat ride on some of the lakes which would be impacted by the project.   The three hours I rode the waves on Junior and Scraggly Lakes were some of the most enjoyable hours of my summer.  Working on ‘wind’ keeps me chained to the computer or on the road traveling, and during the last two years I have missed spending time outdoors and on the water.  The hours spent with friends as we toured those beautiful lakes were well worth the sunburn I received—the only bit of color I got all summer long.

That first evening (Monday) marked the commencement of the public testimony portion of the hearings.  Tuesday was reserved for the technical hearing, with the public testimony concluding that evening.  Citizens spoke overwhelmingly in opposition to the Bowers project.   Most who spoke in favor of the wind development stood to gain financially if the project was approved.  Conversely, many who spoke against the industrial facility believed the project would cause them economic hardship and negatively impact their quality of life.
First Wind’s attorney Juliet Brown (Verrill Dana) spearheaded the company’s defense of their proposed project.  Environmental engineers, consultants, a visual impact expert, survey results…the wind developer pulled out all the stops.  Conservation Law Foundation supported First Wind by speaking in nebulous terms about the positive impact the project would have on reducing greenhouse gas emissions.  They also called an “expert” who attempted to convince Commissioners that wind energy would reduce electricity costs in Maine.

NRCM dropped out as intervenors a few days before the public hearing and on the first night of testimony, Kathy Johnson, North Woods Project Director, testified “neither for nor against” the project.   However, her testimony spoke volumes about the region’s value:

“Both the applicant and Palmer (LURC’s Scenic Expert) underrate the significance of the nine lakes with significant or outstanding scenic resources…The Appalachian Mountain Club…describes this loop as “one of the best quiet-water loop trails in the state, especially when one detours for a few days into Scraggly Lake…””

The PPDLW group, working independently and without legal representation, presented a powerful case; explaining to the Commissioners that the beauty and uniqueness of the watershed was the lifeblood of the region.  Residents’ livelihoods are tied to the lakes, many of which are classified as scenic resources of state or national significance.  Testifying for PPDLW and David Corrigan were local guides and sporting camp owners who live and work in the area.  No others could defend the region with such knowledge and expertise.

Tick-tock-tick-tock…

The public hearing concluded in Bangor on July 6th, and parties had until July 26th to respond to the comments submitted.  Closing statements were presented at the October 5th LURC Commissioners’ meeting in Ellsworth and deliberations began immediately following those statements.  It was decided on that day to continue deliberations in Lincoln on October 19th and to take a “straw vote” at that time; in order to instruct staff on what type decision document to draft for the December 7th meeting.  The 270 day window is closing fast.

Tick-tock-tick-tock…
On Wednesday, October 19, 2011, LURC Commissioners voted unanimously to instruct staff to prepare a decision document to deny First Wind a permit to build a wind energy project on Bowers Mountain in Carroll Plantation and Dill Hill in Kossuth Township.  They plan to meet in Lincoln again on December 7th to take the official vote, but for all intents and purposes, the case has concluded.

The Bowers wind project is the first industrial wind project to get denied since LD 2283 was passed in May of 2008.  We’ve heard LURC commissioners say it over and over again: They feel as though the Wind Energy Act is a directive to approve grid-scale wind projects.  The Legislature created LURC and the Legislature passed the expedited permitting law.  They have stumbled over that fact often in the last several years.  And yet, in March, Department of Conservation Commissioner Bill Beardsley said this to the Commissioners:

The important factor to me is that your board-- you all can say ‘no’. There is nothing about the expedited process that says it’s easier to get a ‘yes’.” 

What a relief it was on Wednesday to see that they ‘get it’.  That they understand and agree that just because wind facilities have been given special privileges--it doesn’t mean they are suitable to be placed on every horizon in the state of Maine.

LURC Commissioners have indicated they intend to deny the Bowers project, but that doesn’t mean that opponents are resting on their laurels and enjoying a well-deserved respite.  Citizens have witnessed the shenanigans of the wind industry time and again, and they are wondering what will come next.  It hasn’t escaped notice that Ms. Browne was also Trans-Canada’s attorney of record during the Sisk Mountain application process last year. 

In July of 2010 LURC decided to DENY the Sisk Mountain wind project, and instructed staff to draft a decision document to that effect for the August 4, 2010 meeting.

But once LURC’s straw vote was taken, Trans-Canada’s attorneys scrabbled to find ways to ‘mitigate’ the damage to the environment that the Sisk wind project would cause and they quickly created a new, revised application which reduced the number of turbines in the development.

Unfortunately, LURC was swayed by the developer’s new arguments and new application and they granted Trans-Canada’s permit for the Sisk Wind project in January of 2011.  (The Friends of the Boundary Mountains have appealed LURC’s decision to the Law Court and their case was heard on September 14th.  They are currently waiting for the judges to make a ruling.)

The two projects and the issues involved are vastly different and yet, the fact that LURC was convinced to change their vote is troublesome to citizens who spend vast amounts of time, energy, emotion and financial resources to make their case against a particular development.  If a wind company can simply change the game mid-stream by supplying an altered application or paying more ‘mitigation’ funds, where is the due process?  Is that not favoring large and powerful corporations while disenfranchising Maine citizens?

I don’t believe First Wind can salvage the Bowers project.  There are no measures which could be taken which would make the project acceptable in the Downeast Lakes watershed.  Scenic impact simply cannot be mitigated. 
The LURC Commissioners were touring the Downeast Lakes in a pontoon boat on that same late June afternoon when I got my sunburn.  They explored the inlets and coves, viewed the islands and wooded shorelines.  When the flotilla’s motors were off, Commissioners heard the sweet sound of water lapping against the hull and the haunting call of nesting loons.  They felt the warm breeze lift their hair and the hot sun kiss their cheeks.  They watched the clouds scudding through the azure sky and viewed the jagged peaks of evergreens on the horizons. 

There is simply no way to mitigate that.

These are the words Governor LePage spoke in Rockport on June 18th  when referring to industrial wind projects:

"They are doing an awful lot of damage to our quality of life, our mountains… I don't think it's going to lower the cost of energy.  I think in 10 years we're going to be like Sweden and Denmark and we're going to be swearing at ourselves."

Let’s not wait ten years.  Let’s not suffer regret because we sat back and did nothing.  Let’s take a page from the playbook of the PPDLW and protect and preserve Maine now, before 300 miles of our mountains and thousands of acres forest and shorelines are sacrificed for massive, inefficient, unreliable and extremely expensive wind turbines.  Let’s forge ahead and work to encourage an energy policy based on science and economics.  In doing so, our Legislature will be convinced to repeal that damaging law which set this travesty in motion.  The Wind Energy Act was based on a presumption of benefits—many of which have been shown to be inaccurate or non-existent.  It’s time for facts to drive our policies and not vague assumptions that wind is a panacea for our energy concerns.

LURC Commissioners made a wise decision about a difficult issue.  Their job is not easy and I believe they agonize over their votes each time they must cast them.  I hope that they feel at peace with the verdict they arrived at for the Bowers project. 

I have no doubt that an hour spent on Pleasant or Junior or Scraggly Lake would remind them of exactly what tranquility is all about.

7 comments:

  1. Karen, wonderful piece - thanks for doing this. It has been a monumental couple of years since we first learned of the met towers on Bowers. We are grateful for your commitment to this issue, and your friendship, and your help. And I still think you should run for Governor! - Kay C.

    ReplyDelete
  2. A wonderful write up--and a clear picture of the process. Thank you, Karen.

    For the many good people who have dedicated their blood, sweat, and tears [not to mention a lot of time and money],to defending this region, LURC's recent vote was an afirmation that the State of Maine may yet be worth saving.

    Let's just hope that politics and money don't change that.............

    DC

    ReplyDelete
  3. Outstanding piece. But you unfairly diminished the role YOU played in achieving that 'deny vote'. Thank you.

    ReplyDelete
  4. Hey, Kay and DC and Gary.

    Thanks for checking in and commenting.

    There is no question that Maine is worth saving; we have the market cornered when it comes to "quality of place"... and quality of people. Of course, I'm biased--but I'm allowed to be on my blog. :o)

    Yep... one of our friends wrote last night and said "It takes a village to herd cats." We'll get there, but it will take the efforts and commitment of many. But we've proof that it works--just look at Bowers!

    xoxo Kaz

    ReplyDelete
  5. Terrific summation of the process and the decision. Shortened slightly, it would make a terrific LTE piece to be sent statewide.

    One of the biggest tragedies of this wind power issue is that the developers and their attorneys go into small towns and planatations and before they're through they've intentionally pitted brother against brother, fathers against son, and cause the destrution of many otherwise healthy friendships. That's a tragedy.

    But the other side of the coin is that at least among the wind project opponents, we've all created many new friends. Kaz, you have our sincere gratitude for all your help, and we hope that our friendship lasts a lot longer than these insipid wind turbines. DC, that goes for you also. Proud to call you both "fiends".

    Kevin G.
    PPDLW

    ReplyDelete
  6. And I'm proud to be called 'fiend', by golly!

    Hehehe....sorry, Kevin, but I get caught on typos ALL the time, so it's nice when I can tease someone else about it. Yesterday, the New Portland Community FB page said there would be a scarecrow contest and boobing for apples in the town park.

    Y'gotta love the English language. :o) And clumsy fingers...

    I count myself lucky to be your friend, you know. :o)

    ReplyDelete
  7. Rereading this the night before yet another Bowers hearing. The beat goes on. Thank you for writing this lovely piece. Gives us a lift as we burn the midnight oil. - Kay

    ReplyDelete