Below: The cover letter for the denial document sent to First Wind by the Maine Department of Environmental Protection...
The first Bowers Public Hearing in June of 2011 (LURC also denied the project.) |
August
2013
Champlain
Wind, LLC
129
Middle Street, Floor 3
Portland,
Maine 04101
ATTN:
Mr. Neil Kiely
RE:
Site Location of Development Act/ Natural Resources Protection Act
Applications, Carroll Plantation and Kossuth Township,
#L-25800-24-A-N/#L-25800-TE-B-N/#L-25800-IW-C-N Denial
Sign for a free First Wind-sponsored dinner provided prior to the second Public Hearing for those who would testify on behalf of the Bowers project. |
Dear
Mr. Kiely:
Please
find enclosed a signed copy of the denial of your Department of Environmental
Protection
applications
for permits under the Site Location of Development Act and the Natural
Resources
Protection
Act. You will note that the denial includes a description of your project, and
findings of fact that relate to the criteria the Department used in evaluating
your project. The Department reviews every application thoroughly and strives
to formulate reasonable findings of fact within the context of the Department’s
environmental laws. You will also find attached some materials that describe
the Department’s appeal procedures for your information.
Maine citizens testifies about the negative visual impacts of grid-scale wind in the pristine Downeast Lakes region. |
If you
have any questions or concerns on how the Department processed this application
please get in touch with me directly. I can be reached at (207) 446-9026 or at
Jim.R.Beyer@maine.gov.
Sincerely,
James
R. Beyer, Regional Licensing and Compliance Manager
Division
of Land Resource Regulation
Bureau
of Land & Water Quality
Press Conference in Lincoln about the negative impacts wind turbines would have on the Bowers region's natural resource-based economy and locals' quality of life. |
No comments: